21INR0240 · Wind · Stephens County

La Casa Wind

La Casa Wind is a 148 MW wind project in Stephens County, Texas, connecting at New switching station: 138kV Graham Plant Switch - Breckenridge - Leon Switch. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 11/30/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
21INR0240
Capacity
148 MW
Fuel
Wind (WT)
Interconnecting entity
LA CASA WIND, LLC
Projected COD
11/30/2026
Entered queue
12/28/2018
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 11/14/2025
    Energization Approved → Sync Approved
  • 10/31/2025
    IA Signed → Energization Approved
  • 09/22/2023
    FIS Requested → FIS Approved
  • 09/07/2023
    FIS Approved → IA Signed
  • 12/29/2018
    Screening → FIS Requested
  • 12/28/2018
    Entered the queue with 148 MW, projected COD 11/30/2026

Other projects at this substation

No other projects at this substation.