21INR0031 · Solar · Fisher County

Indigo Solar

Indigo Solar is a 150 MW solar project in Fisher County, Texas, connecting at tap 345 kV 68001 Claytonville – 68004 Phantom Hill Circuit 2. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 09/17/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
21INR0031
Capacity
150 MW
Fuel
Solar (PV)
Interconnecting entity
Innovative Solar 245, LLC
Projected COD
09/17/2027
Entered queue
09/27/2018
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/15/2020
    FIS Requested → IA Signed
  • 05/15/2019
    Screening → FIS Requested
  • 09/27/2018
    Entered the queue with 150 MW, projected COD 09/17/2027

Other projects at this substation

Indigo StorageBESS60 MWIA Signed
Indigo Storage 2BESS60 MWIA Signed
Indigo Storage 3BESS60 MWIA Signed
Indigo Storage 4BESS60 MWIA Signed