LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
20INR0266 · Solar · Calhoun County

Tres Bahias Solar

Tres Bahias Solar is a 195 MW solar project in Calhoun County, Texas, connecting at 8140 Joslin 138kV. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 08/31/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
20INR0266
Capacity
195 MW
Fuel
Solar (PV)
Interconnecting entity
Tres Bahias Solar Power LLC
Projected COD
08/31/2026
Entered queue
03/26/2019
ERCOT zone
COASTAL
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/12/2023
    Energization Approved → Sync Approved
  • 06/26/2023
    IA Signed → Energization Approved
  • 01/21/2022
    FIS Requested → FIS Approved
  • 08/07/2020
    FIS Approved → IA Signed
  • 06/03/2019
    Screening → FIS Requested
  • 03/26/2019
    Entered the queue with 195 MW, projected COD 08/31/2026

Other projects at this substation

No other projects at this substation.