LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
20INR0248 · Solar · Brazoria County

DAMAZO (Second Division) SOLAR

DAMAZO (Second Division) SOLAR is a 100 MW solar project in Brazoria County, Texas, connecting at Tap 138 kV SANBER_POI_8 (Bus# 43110) to WEST COLUMBIA (Bus# 43380) Ckt 60 Line. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 12/31/2025.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
20INR0248
Capacity
100 MW
Fuel
Solar (PV)
Interconnecting entity
TX Gulf Solar 1 LLC
Projected COD
12/31/2025
Entered queue
03/28/2019
ERCOT zone
COASTAL
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/17/2024
    Energization Approved → Sync Approved
  • 10/08/2024
    IA Signed → Energization Approved
  • 10/28/2022
    FIS Requested → FIS Approved
  • 10/14/2020
    FIS Approved → IA Signed
  • 07/29/2019
    Screening → FIS Requested
  • 03/28/2019
    Entered the queue with 100 MW, projected COD 12/31/2025

Other projects at this substation

Second Division StorageBESS0 MWFIS Requested