20INR0241 · Solar · Jones County
Crowded Star Solar
Crowded Star Solar is a 219 MW solar project in Jones County, Texas, connecting at tap 345kV 68001 Claytonville – 68004 Phantom Hill c2 (New Substation: Open Sky 68014). ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 08/17/2026.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 20INR0241
- Capacity
- 219 MW
- Fuel
- Solar (PV)
- County
- Jones County
- Interconnecting entity
- Jones City Solar, LLC
- Projected COD
- 08/17/2026
- Entered queue
- 01/21/2019
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 05/28/2026Energization Approved → Sync Approved
- 04/22/2026IA Signed → Energization Approved
- 11/05/2024FIS Requested → FIS Approved
- 12/17/2019FIS Approved → IA Signed
- 05/22/2019Screening → FIS Requested
- 01/21/2019Entered the queue with 219 MW, projected COD 08/17/2026
Other projects at this substation
| Crowded Star Solar II | Solar | 190 MW | Sync Approved |