Crowded Star Solar

Crowded Star Solar is a 219 MW solar project in Jones County, Texas, connecting at tap 345kV 68001 Claytonville – 68004 Phantom Hill c2 (New Substation: Open Sky 68014). ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 08/17/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
20INR0241
Capacity
219 MW
Fuel
Solar (PV)
Interconnecting entity
Jones City Solar, LLC
Projected COD
08/17/2026
Entered queue
01/21/2019
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 05/28/2026
    Energization Approved → Sync Approved
  • 04/22/2026
    IA Signed → Energization Approved
  • 11/05/2024
    FIS Requested → FIS Approved
  • 12/17/2019
    FIS Approved → IA Signed
  • 05/22/2019
    Screening → FIS Requested
  • 01/21/2019
    Entered the queue with 219 MW, projected COD 08/17/2026

Other projects at this substation

Crowded Star Solar IISolar190 MWSync Approved