LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
20INR0129 · Wind · Bee County

Foxtrot Wind

COD delayed 1×

Foxtrot Wind is a 268 MW wind project in Bee County, Texas, connecting at AEP 88689 Tango 345kV station. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 12/31/2026. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
20INR0129
Capacity
268 MW
Fuel
Wind (WT)
Interconnecting entity
Lincoln Clean
Projected COD
12/31/2026
Entered queue
07/26/2018
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 08/31/2026 → 12/31/2026 (+4 months)
  • 03/09/2022
    Energization Approved → Sync Approved
  • 02/23/2022
    IA Signed → Energization Approved
  • 07/30/2021
    FIS Requested → FIS Approved
  • 05/05/2020
    FIS Approved → IA Signed
  • 07/26/2018
    Entered the queue with 268 MW, projected COD 08/31/2026
  • 07/26/2018
    Screening → FIS Requested

Other projects at this substation