20INR0129 · Wind · Bee County
Foxtrot Wind
COD delayed 1×
Foxtrot Wind is a 268 MW wind project in Bee County, Texas, connecting at AEP 88689 Tango 345kV station. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 12/31/2026. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 20INR0129
- Capacity
- 268 MW
- Fuel
- Wind (WT)
- Substation
- AEP 88689 Tango 345kV station
- County
- Bee County
- Interconnecting entity
- Lincoln Clean
- Projected COD
- 12/31/2026
- Entered queue
- 07/26/2018
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 08/31/2026 → 12/31/2026 (+4 months)
- 03/09/2022Energization Approved → Sync Approved
- 02/23/2022IA Signed → Energization Approved
- 07/30/2021FIS Requested → FIS Approved
- 05/05/2020FIS Approved → IA Signed
- 07/26/2018Entered the queue with 268 MW, projected COD 08/31/2026
- 07/26/2018Screening → FIS Requested
Other projects at this substation
No other projects at this substation.