20INR0106 · Solar · Falls County
Wang Solar SLF
COD delayed 1×
Wang Solar SLF is a 145 MW solar project in Falls County, Texas, connecting at tap 345kV 3409 LakeCr1 - 3414 TempSS. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 01/31/2029. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 20INR0106
- Capacity
- 145 MW
- Fuel
- Solar (PV)
- Substation
- tap 345kV 3409 LakeCr1 - 3414 TempSS
- County
- Falls County
- Interconnecting entity
- BT Yixin Solar, LLC
- Projected COD
- 01/31/2029
- Entered queue
- 06/14/2018
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 03/31/2026 → 01/31/2029 (+34 months)
- 08/29/2018Screening → FIS Requested
- 06/14/2018Entered the queue with 145 MW, projected COD 03/31/2026
Other projects at this substation