LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
20INR0050 · Solar · Castro County

Castro Solar

COD delayed 1×

Castro Solar is a 225 MW solar project in Castro County, Texas, connecting at 23912 Ogallala 345kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 04/18/2029. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
20INR0050
Capacity
225 MW
Fuel
Solar (PV)
Interconnecting entity
Castro Solar One, LLC
Projected COD
04/18/2029
Entered queue
02/08/2018
ERCOT zone
PANHANDLE
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 09/20/2028 → 04/18/2029 (+7 months)
  • 11/30/2020
    FIS Requested → IA Signed
  • 05/15/2018
    Screening → FIS Requested
  • 02/08/2018
    Entered the queue with 225 MW, projected COD 09/20/2028

Other projects at this substation

No other projects at this substation.