20INR0050 · Solar · Castro County
Castro Solar
COD delayed 1×
Castro Solar is a 225 MW solar project in Castro County, Texas, connecting at 23912 Ogallala 345kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 04/18/2029. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 20INR0050
- Capacity
- 225 MW
- Fuel
- Solar (PV)
- Substation
- 23912 Ogallala 345kV
- County
- Castro County
- Interconnecting entity
- Castro Solar One, LLC
- Projected COD
- 04/18/2029
- Entered queue
- 02/08/2018
- ERCOT zone
- PANHANDLE
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 09/20/2028 → 04/18/2029 (+7 months)
- 11/30/2020FIS Requested → IA Signed
- 05/15/2018Screening → FIS Requested
- 02/08/2018Entered the queue with 225 MW, projected COD 09/20/2028
Other projects at this substation
No other projects at this substation.