20INR0012 · Solar · Haskell County
Lueders Solar
Lueders Solar is a 40 MW solar project in Haskell County, Texas, connecting at Tap 138kV 6161 Paint Creek - 6200 Ft Phantom. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/31/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 20INR0012
- Capacity
- 40 MW
- Fuel
- Solar (PV)
- County
- Haskell County
- Interconnecting entity
- Innovative Solar 75
- Projected COD
- 12/31/2029
- Entered queue
- 07/11/2017
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/20/2017Screening → FIS Requested
- 07/11/2017Entered the queue with 40 MW, projected COD 12/31/2029