LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
19INR0175 · Wind · Castro County

Shifting Gale Wind

Withdrawn

Shifting Gale Wind is a 289 MW wind project in Castro County, Texas, with no point of interconnection listed. It is no longer active in ERCOT's interconnection queue.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
19INR0175
Capacity
289 MW
Fuel
Wind
Substation
Not listed
Interconnecting entity
Not listed
Projected COD
n/a
Entered queue
01/28/2025
ERCOT zone
n/a
Size category
n/a

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 01/28/2025
    Listed as inactive

Other projects at this substation

No other projects at this substation.