19INR0174 · Wind · Howard County
Elbow Creek repower
Elbow Creek repower is a 0 MW wind project in Howard County, Texas, connecting at 1058 Longshore 345kV. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 03/31/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 19INR0174
- Capacity
- 0 MW
- Fuel
- Wind (WT)
- Substation
- 1058 Longshore 345kV
- County
- Howard County
- Interconnecting entity
- Elbow Creek Wind Project, LLC
- Projected COD
- 03/31/2027
- Entered queue
- 11/30/2007
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 06/27/2019IA Signed → Sync Approved
- 09/17/2018FIS Requested → FIS Approved
- 07/19/2018Screening → FIS Requested
- 11/30/2007Entered the queue with 0 MW, projected COD 03/31/2027
- 11/30/2007FIS Approved → IA Signed
Other projects at this substation
| Odessa Energy Storage | BESS | 203 MW | FIS Requested |