19INR0134 · Solar · Brazoria County

Cottonwood Bayou Solar

COD delayed 1×

Cottonwood Bayou Solar is a 351 MW solar project in Brazoria County, Texas, connecting at tap 138kV 42870 Liverpool - 43070 Petson. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 10/30/2026. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
19INR0134
Capacity
351 MW
Fuel
Solar (PV)
Interconnecting entity
Cottonwood Bayou Solar, LLC
Projected COD
10/30/2026
Entered queue
09/22/2017
ERCOT zone
COASTAL
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 08/29/2026 → 10/30/2026 (+2 months)
  • 05/29/2024
    Energization Approved → Sync Approved
  • 05/01/2024
    IA Signed → Energization Approved
  • 04/27/2023
    FIS Requested → FIS Approved
  • 11/13/2019
    FIS Approved → IA Signed
  • 02/15/2018
    Screening → FIS Requested
  • 09/22/2017
    Entered the queue with 351 MW, projected COD 08/29/2026