ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
19INR0110 · Solar · Angelina County

Azalea Springs Solar

COD delayed 1×

Azalea Springs Solar is a 181 MW solar project in Angelina County, Texas, connecting at tap 138kV Jim English – Lufkin Chipper Mill. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 11/01/2026. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
19INR0110
Capacity
181 MW
Fuel
Solar (PV)
Interconnecting entity
AZALEA SPRINGS SOLAR PARK LLC
Projected COD
11/01/2026
Entered queue
07/26/2017
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 07/15/2026 → 11/01/2026 (+4 months)
  • 02/11/2025
    Energization Approved → Sync Approved
  • 01/29/2025
    IA Signed → Energization Approved
  • 04/30/2024
    FIS Requested → FIS Approved
  • 09/14/2023
    FIS Approved → IA Signed
  • 03/15/2018
    Screening → FIS Requested
  • 07/26/2017
    Entered the queue with 181 MW, projected COD 07/15/2026

Other projects at this substation