19INR0110 · Solar · Angelina County
Azalea Springs Solar
COD delayed 1×
Azalea Springs Solar is a 181 MW solar project in Angelina County, Texas, connecting at tap 138kV Jim English – Lufkin Chipper Mill. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 11/01/2026. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 19INR0110
- Capacity
- 181 MW
- Fuel
- Solar (PV)
- County
- Angelina County
- Interconnecting entity
- AZALEA SPRINGS SOLAR PARK LLC
- Projected COD
- 11/01/2026
- Entered queue
- 07/26/2017
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 07/15/2026 → 11/01/2026 (+4 months)
- 02/11/2025Energization Approved → Sync Approved
- 01/29/2025IA Signed → Energization Approved
- 04/30/2024FIS Requested → FIS Approved
- 09/14/2023FIS Approved → IA Signed
- 03/15/2018Screening → FIS Requested
- 07/26/2017Entered the queue with 181 MW, projected COD 07/15/2026