19INR0035 · Solar · Runnels County
Norton Solar
Norton Solar is a 128 MW solar project in Runnels County, Texas, connecting at 60451 Garnet 138kV. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 11/24/2025.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 19INR0035
- Capacity
- 128 MW
- Fuel
- Solar (PV)
- Substation
- 60451 Garnet 138kV
- County
- Runnels County
- Interconnecting entity
- TAI Norton Solar, LLC
- Projected COD
- 11/24/2025
- Entered queue
- 03/06/2017
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 08/06/2025Energization Approved → Sync Approved
- 07/24/2025IA Signed → Energization Approved
- 10/29/2024FIS Requested → FIS Approved
- 06/20/2019FIS Approved → IA Signed
- 11/08/2017Screening → FIS Requested
- 03/06/2017Entered the queue with 128 MW, projected COD 11/24/2025
Other projects at this substation
No other projects at this substation.