19INR0023 · Wind · Willacy County
Monte Alto 2 Wind
Monte Alto 2 Wind is a 199 MW wind project in Willacy County, Texas, connecting at tap 345kV 8318 Rio Hondo - 8383 N Edinburg. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/31/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 19INR0023
- Capacity
- 199 MW
- Fuel
- Wind (WT)
- County
- Willacy County
- Interconnecting entity
- Monte Alto Windpower, LLC
- Projected COD
- 12/31/2028
- Entered queue
- 11/04/2016
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 03/22/2022FIS Requested → IA Signed
- 03/23/2017Screening → FIS Requested
- 11/04/2016Entered the queue with 199 MW, projected COD 12/31/2028