LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
19INR0002 · Solar · Upton County

Grandfalls Solar

Grandfalls Solar is a 176 MW solar project in Upton County, Texas, connecting at 842 King Mountain Station 345kV. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 11/25/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
19INR0002
Capacity
176 MW
Fuel
Solar (PV)
Interconnecting entity
King Mountain Solar, LLC
Projected COD
11/25/2026
Entered queue
05/24/2016
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 07/15/2026
    Energization Approved → Sync Approved
  • 06/24/2026
    IA Signed → Energization Approved
  • 12/17/2025
    FIS Requested → FIS Approved
  • 01/23/2025
    FIS Approved → IA Signed
  • 05/24/2016
    Entered the queue with 176 MW, projected COD 11/25/2026
  • 05/24/2016
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.