18INR0069 · Wind · Pecos County

Indian Mesa repower

Indian Mesa repower is a 9.3 MW wind project in Pecos County, Texas, connecting at 76019 Indian NWP 138kV. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 12/31/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
18INR0069
Capacity
9.3 MW
Fuel
Wind (WT)
Interconnecting entity
Nextera
Projected COD
12/31/2026
Entered queue
05/22/2018
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 12/04/2018
    FIS Approved → IA Signed
  • 11/02/2018
    IA Signed → Sync Approved
  • 10/03/2018
    FIS Requested → FIS Approved
  • 05/22/2018
    Entered the queue with 9.3 MW, projected COD 12/31/2026
  • 05/22/2018
    Screening → FIS Requested

Other projects at this substation