18INR0031 · Wind · Nolan County
Maryneal Wind
Maryneal Wind is a 182 MW wind project in Nolan County, Texas, connecting at 71050 Bitter Creek 345kV. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 08/31/2026.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 18INR0031
- Capacity
- 182 MW
- Fuel
- Wind (WT)
- Substation
- 71050 Bitter Creek 345kV
- County
- Nolan County
- Interconnecting entity
- Maryneal Windpower, LLC
- Projected COD
- 08/31/2026
- Entered queue
- 05/26/2016
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 04/23/2021Energization Approved → Sync Approved
- 01/08/2021IA Signed → Energization Approved
- 01/31/2020FIS Requested → FIS Approved
- 01/31/2020FIS Approved → IA Signed
- 07/22/2016Screening → FIS Requested
- 05/26/2016Entered the queue with 182 MW, projected COD 08/31/2026