ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
17INR0070 · Wind · Pecos County

Desert Sky repower

Desert Sky repower is a 7.2 MW wind project in Pecos County, Texas, connecting at two LCRA 138kV. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 05/16/2023.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
17INR0070
Capacity
7.2 MW
Fuel
Wind (WT)
Substation
two LCRA 138kV
Interconnecting entity
DESERT SKY WIND FARM LLC
Projected COD
05/16/2023
Entered queue
11/08/2017
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/06/2019
    IA Signed → Sync Approved
  • 10/18/2018
    FIS Approved → IA Signed
  • 02/06/2018
    FIS Requested → FIS Approved
  • 11/08/2017
    Entered the queue with 7.2 MW, projected COD 05/16/2023
  • 11/08/2017
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.