16INR0112 · Wind · La Salle County
Loma Pinta Wind
Loma Pinta Wind is a 197 MW wind project in La Salle County, Texas, connecting at 5705 Fowlerton 138kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/31/2026.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 16INR0112
- Capacity
- 197 MW
- Fuel
- Wind (WT)
- Substation
- 5705 Fowlerton 138kV
- County
- La Salle County
- Interconnecting entity
- Enerverse
- Projected COD
- 12/31/2026
- Entered queue
- 05/18/2015
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 12/13/2017FIS Requested → IA Signed
- 05/18/2015Entered the queue with 197 MW, projected COD 12/31/2026
- 05/18/2015Screening → FIS Requested
Other projects at this substation
| Loma Pinta Solar | Solar | 203 MW | FIS Requested |