Counties / Texas
Morris County power projects
Morris County, Texas has 1 active power project totalling 166 MW in ERCOT's interconnection queue as of the October 2026 report. Natural gas is the largest share at 166 MW (100%). The largest single project is LONE STAR INDUSTRIAL PARK GAS POWER PROJECT (166 MW natural gas). 0 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.
Active projects
1
0.2 GW capacity
IA signed or later
0
0% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
0
since Sep 2026
Changes in Morris County
No changes in the reports compared so far.
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| LONE STAR INDUSTRIAL PARK GAS POWER PROJECT | Gas | 166 | 1795 Monticello SES 138kV | FIS Requested | 05/11/2028 |
For residents and landowners
- What power projects are planned in Morris County?
- ERCOT's October 2026 report lists 1 active project in Morris County totalling 166 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.