ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Counties / Texas

Montague County power projects

Montague County, Texas has 4 active power projects totalling 1,014 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 713 MW (70%). The largest single project is Prairie Branch BESS (310 MW battery storage). 0 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.

Active projects
4
1.0 GW capacity
IA signed or later
0
0% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
0
since Sep 2026

Changes in Montague County

No changes in the reports compared so far.

All projects

ProjectFuelMWSubstationStageCOD
Prairie Branch BESSBESS310Tap 345kV #1730 Krum West - #6111 Riley Ckt 1FIS Requested12/01/2029
Prairie Branch SolarSolar301Tap 345kV #1730 Krum West - #6111 Riley Ckt 1FIS Requested12/01/2029
Fortissimo BESSBESS203741 Dyemound 138kVFIS Approved04/24/2028
Enfinity PrimroseBESS200(741) DYEMOUND Substation 138kVFIS Requested07/17/2030

For residents and landowners

What power projects are planned in Montague County?
ERCOT's October 2026 report lists 4 active projects in Montague County totalling 1,014 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.