Medina County power projects

Medina County, Texas has 7 active power projects totalling 956 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 745 MW (78%). The largest single project is Devine Mary BESS (201 MW battery storage). 0 projects have signed an interconnection agreement or reached a later stage. 1 project in the county is listed as withdrawn or cancelled.

Active projects
7
1.0 GW capacity
IA signed or later
0
0% of active projects
Withdrawn or cancelled
1
listed by ERCOT
Changes tracked
0
since Sep 2026

Changes in Medina County

No changes in the reports compared so far.

All projects

ProjectFuelMWSubstationStageCOD
Devine Mary BESSBESS2015813 PEARSONSW8 138 kVFIS Requested11/21/2028
Chacon CreekBESS189(#8962) LYTLE4A 138KVFIS Requested10/31/2027
Ranger BESSBESS155SSWG Bus name: CSTROVILESB8 , Bus# : 5804FIS Requested04/29/2029
Dunlay SolarSolar150Tap 138kV 5813 PearsonSW - 5225 HondoFIS Requested12/31/2030
Hondo Arroyo StorageBESS101Tap 138 kV 5225 Hondo - 5813 PearsonFIS Requested07/01/2028
Adam Bryant BESSBESS100Tap 138kV 5225 HONDO – 5819 HONDO CREEKFIS Requested12/01/2027
Hondo Arroyo SolarSolar60Tap 138 kV 5225 Hondo - 5813 PearsonFIS Requested07/01/2028
Spinel SolarSolar30Not listedWithdrawnn/a

For residents and landowners

What power projects are planned in Medina County?
ERCOT's October 2026 report lists 7 active projects in Medina County totalling 956 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.