LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Counties / Texas

Dewitt County power projects

Dewitt County, Texas has 5 active power projects totalling 972 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 616 MW (63%). The largest single project is Shaula I BESS (206 MW battery storage). 2 projects have signed an interconnection agreement or reached a later stage. 2 projects in the county are listed as withdrawn or cancelled.

Active projects
5
1.0 GW capacity
IA signed or later
2
40% of active projects
Withdrawn or cancelled
2
listed by ERCOT
Changes tracked
0
since Sep 2026

Changes in Dewitt County

No changes in the reports compared so far.

All projects

ProjectFuelMWSubstationStageCOD
Shaula I BESSBESS2065380 Shaula 345kVFIS Requested06/01/2028
Shaula I SolarSolar205tap 345kV 5133 Elm Creek - 5915 SO TEX ckt 1IA Signed06/15/2028
Shaula II SolarSolar205tap 345kV 5133 Elm Creek - 5915 SO TEX ckt 1IA Signed06/15/2028
Shaula III SolarSolar205tap 345kV 5133 Elm Creek - 5915 SO TEX ckt 1FIS Requested12/24/2025
Yorktown BESSBESS150(#78575) LCRA Yorktown 138 kVFIS Requested12/16/2028
BAYSIDE II SOLARSolar253Not listedWithdrawnn/a
Bayside 2 BESSBESS252Not listedWithdrawnn/a

For residents and landowners

What power projects are planned in Dewitt County?
ERCOT's October 2026 report lists 5 active projects in Dewitt County totalling 972 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.