Counties / Texas
Comal County power projects
Comal County, Texas has 3 active power projects totalling 867 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 867 MW (100%). The largest single project is Enfinity Redbud Storage (516 MW battery storage). 0 projects have signed an interconnection agreement or reached a later stage. 1 project in the county is listed as withdrawn or cancelled.
Active projects
3
0.9 GW capacity
IA signed or later
0
0% of active projects
Withdrawn or cancelled
1
listed by ERCOT
Changes tracked
0
since Sep 2026
Changes in Comal County
No changes in the reports compared so far.
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Enfinity Redbud Storage | BESS | 516 | 345kV Hays Energy (7043) - 345kV Bergheim (7770) | FIS Requested | 12/18/2029 |
| Englehardt BESS | BESS | 200 | River Oaks (7173) | FIS Requested | 09/01/2027 |
| Short River BESS | BESS | 150 | 7456 LOP3378 138kV | FIS Requested | 04/30/2030 |
| Madrone Energy Storage | BESS | 102 | Not listed | Withdrawn | n/a |
For residents and landowners
- What power projects are planned in Comal County?
- ERCOT's October 2026 report lists 3 active projects in Comal County totalling 867 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.