Counties / Texas
Archer County power projects
Archer County, Texas has 7 active power projects totalling 827 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 500 MW (60%). The largest single project is Red Hollow Renewable Energy Solar SLF (309 MW solar). 1 project has signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.
Active projects
7
0.8 GW capacity
IA signed or later
1
14% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
0
since Sep 2026
Changes in Archer County
No changes in the reports compared so far.
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Red Hollow Renewable Energy Solar SLF | Solar | 309 | Tap 345kV (Bus# 1422) Bowman - (Bus# 17002) Garvey Road | FIS Requested | 04/19/2029 |
| Ringtail Energy Storage | BESS | 204 | Bus # 1446, Lake Wichita, 138 kV | FIS Requested | 12/15/2028 |
| Wichita Falls Energy Storage | BESS | 202 | Tap 345kV 1422 Bowman - 1458 Cobb Switch | FIS Requested | 08/01/2028 |
| Trinity Hills BESS SLF | BESS | 94 | To the 345 kV Garvey Road Switch (#17002) | FIS Requested | 01/24/2028 |
| Shannon Wind Repower | Wind | 18 | 1458 Cobb Switching Station 345 kV | FIS Requested | 09/15/2027 |
| Bobcat Bluff Storage SLF | BESS | 0 | 1475 Windthorst 138 kV | IA Signed | 04/15/2027 |
| Red Hollow Renewable Energy BESS SLF | BESS | 0 | Tap 345kV 1422 Bowman - 17002 Garvey Road | FIS Requested | 04/19/2029 |
For residents and landowners
- What power projects are planned in Archer County?
- ERCOT's October 2026 report lists 7 active projects in Archer County totalling 827 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.